Expert in Total Turnaround Management, RCM, Precom & Commissioning, Bolting, Chemical decontamination


Available for your Consulting and Expert Witness Needs

Western Australia
Australia
Education Work History Consulting Services Expert Witness

Summary of Expertise:

Listed with other top experts in: 

Fully conversant with P & ID's , Column internals, Erection, Hydro testing, Chemical Cleaning and Oil Flushing, Flushing and Dry out Operations, Pre-Commissioning and Commissioning of a Large PetroChemical Complex.

Start-Ups , Shutdowns, Handling Emergencies, and Fire Fighting and Normal Operations & Maintenance of Continuous Process Industries. He performed Decontamination of HF alkylation unit for Samref (Saudi Aramco Mobile refinery) for shut down plant maintenance. He performed De contamination of the columns and vessels in Saudi Chevron Phillips during shut down Feb 2007, October 2007 reduces the gas freeing and release for maintenance 50% less time. He performed Pre commissioning works for Saudi Aramco GOSP 1 & 2, Qatif Producing Facilities. As a Contractor for Pre Commissioning to Snamprogetti S. p. A. Milanese, Italy. and for Arabian CB & I. Planning and Work Package Preparation in Progress and the Pre commissioning work. Prepared Checklist & Forms for Precommissioning and Site acceptance and inspection for startup. The GOSP 1 consist of Gas Oil Separation Plant, Water Oil Separation Plant, Water Injection Plant, Gas Gathering Plant and Utilities.

Plant Operation Experience:

Prefractionation Separation of C10 – C13 from S. K. Units.

Hydrodesulfurization units.

Molecular Extraction – Molex with continuous operation by having a Rotary Valve System of UOP process.

Platformer Paraffin – Olefin Convertion – Pacol. Detergent Alkylation system with catalyst of HF Acid.

Hot Oil Circulation System – Balanced draft Oil fired multipass heater using Therm 600 as heating media with a heat load of 40 million Kcal/hr.

LPG Bulk handling and Bottling Plant.

Lube Oil Blending and Manufacturing Plant.

Steam generation, Demineralising unit, Cooling Tower and Effluent treatment system with API oil separation system.

Product handling and storage.

 • 

chemical plant operation

 • 

chemical plant start-up

 • 

hydrofluoric acid catalyzed alkylation

 • 

petroleum processing

 • 

precommissioning

 • 

chemical decontamination


Show Secondary and Basic Areas of Expertise

Education:
Year   Degree   Subject   Institution  
1991   Post Graduate Diploma   Petrochemical Engineering   Central Institute Of Management  
1986   Diploma   Chemical Technology   Board Of Technical Education  
2006   B Tech   Chemical Engineering   Sri Raghavendra Research Institute  

Work History:
Years   Employer   Department   Title   Responsibilities

2008 to

 

(Undisclosed)

 

Technical Services

 

Project Manager

 

Presently assigned as Project Manager in Barrup Fertilizers Pty Ltd, operating the largest Ammonia plant in Australia for a Major shutdown planned during July 2008

2003 to 2008

 

Mohammad Al Mojil Group

 

Technical Services

 

Manager

 

He is responsible for preparation of Bid Packages, Work Packages, Operation manuals and Procedures, Estimation, Project Planning and provide Technical support for the Services Division which perform Maintenance, precommissioning works for Oil and Gas Industries in the Middle East.

1998 to 2003

 

R R Dyechem

 

Production

 

Manager

 

He is responsible for Regular Inspection, Operation of the Plant, Collecting Data, Inspecting for Abnormalities and Planning Schedule for Preventive Maintenance and ATA, Handover the Equipments for Maintenance and Lining Up after Maintenance and Ensuring Safety at all times for the Lube Oil Plant located at Chennai India.

1995 to 1998

 

Feena Petroproducts Ltd

 

Production

 

Supervisor

 

He is responsible for Operation, Maintenance, and Commissioning of LPG Storage and Bottling Facilities

1986 to 1995

 

Tamil Nadu Petroproducts Ltd

 

Operation

 

Engineer

 

He is responsible for Regular Inspection, Operation of the Plant, Collecting Data, Inspecting for Abnormalities and Planning Schedule for Preventive Maintenance and ATA, Handover the Equipments for Maintenance and Lining Up after Maintenance and Ensuring Safety at all times for the large Petrochemical complex located at Chennai India. Precommissioning and Commissioning of Large petrochemical complex.


Consulting Services:
Click the green button above to contact Expert for a free initial screening call regarding your expert consulting needs.  Expert is available for consulting to corporate, legal and government clients.  Remember, your initial screening call to speak with Expert is free.

Expert Witness:
Click the green button above to contact Expert for a free initial screening call regarding expert testimony, litigation consulting and support, forensic services, or any related expert witness services.  A few litigation needs include product liability, personal injury, economic loss, intellectual property (patent, trademark, trade secret, copyright), and insurance matters.  Remember, your initial screening call to speak with Expert is free.

Additional Skills and Services:
Other Skills and Services

Pre commissioning and Commissioning of process plants.


 